Town Hall January 12, 2022
Scope of Work
- Phase 1 Demo (Superstructure)
- Phase 2 Demo (Below Grade Demo)
Estimated Schedule Dates
- Demo Lower Canopy – Week of 1-24-2022
- Demo Skin N Elevation –Week of 1-31–2022
- Demo Remaining Canopies – Week of 2-07-2022
- Demo Main Concrete Structure – Week of 2-14-2022
- Hauling C&D Off Site Throughout – Week of 3-7-2022