Moving on Up

Moving on Up

Moving on Up About The Novus team has been hard at work as we continue our progress up the building. We just finished the 3rd pour on the 4th elevated deck which is the future floor of 14 apartment units and multiple parking spaces....
First Elevated Deck Pour Complete

First Elevated Deck Pour Complete

First Elevated Deck Pour Complete About Earlier this month, we had our first elevated deck pour on The NOVUS. The pour itself was about 400 cubic yards and was supported by Peri Shoring. All the concrete poured on this deck was a 6,000psi mix and this is our only...
Word on the Street – The Novus

Word on the Street – The Novus

Word on the Street – The Novus Agenda 1. Team Introductions 2. Project Health and Safety 3. Project Update (Novus.Samet411.com)a. Aerial Photosb. Schedule Update – Work Underway· Deep Foundations (Keller)· Matt Foundations and Basement Walls (Lithko)·...
Setting the Bar

Setting the Bar

Setting the Bar About Rebar (Reinforcement Bar) is a steel rod that is used to strengthen concrete. It comes in various lengths and thicknesses. The ridges or bumps allow the rebar to bond well with the concrete.   On The Novus Project, we anticipate fabricating and...
A Different Perspective

A Different Perspective

A Different Perspective About What’s in the picture? The work underway is preparing for what’s coming – the superstructure: deep foundations (Keller), rock and soil excavation (MIS), underground electrical (PDI), layout for concrete and building...